Early completion bonuses

Thursday, June 3rd, 2010

Some clients may insist on having liquidated damages set at a substantial amount under the home building contract ($300 per week and upwards), and there is nothing wrong with this practice.  We all recognise that the client may suffer some loss if the builder is late in completing the project.

However, the builder too can play the same game.  Where a client insists on substantial liquidated damages, the builder may agree to this, on the condition that if the project is completed early, the client must then pay the builder the same amount as an early completion bonus, given that the client will have the benefit of the project at an earlier date.  Keep this tip up your sleeve – one day you may have to use it.



To receive our FREE E-News Bulletin, enter your email address and press ‘Submit’              

Online CPD Courses
CPD Seminars
Online Building Contracts
OHS System
Home Warranty Insurance